OSHA Table A lists 32-0 for a 16K5 joist and NM for a 16K6. A 16K5 will span 34 ft-0 in. What erection-bridging action is required before the hoisting cables may be released?
Correct Answer:
Install a row of bolted diagonal erection bridging near midspan and anchor it

Access more questions from this quiz