Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
ATI Nursing
CNA & Nurse Aide
NREMT & EMS
ACLS
BLS
CPR
Quizzes
Study Guides
Flashcards
Packages
0
Log In
Register
Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
Quizzes
Study Guides
Flashcards
Packages
Contact
Cart
0
Log In
Register
CITB Temporary Works Coordinator (TWCTC) Practice Questions - CITB Temporary Works Coordinator Training Course Assessment (TWCTC) Exam
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 5
What is the main duty of the Principal Designer under CDM 2015 in relation to temporary works during the pre-construction phase?
To supervise the daily installation of trench support systems on site.
To plan, manage, monitor, and coordinate health and safety during pre-construction, ensuring foreseeable risks associated with temporary works interfaces are eliminated or controlled.
To sign off Permits to Load for all falsework and heavy propping.
To supply formwork materials and equipment to the Principal Contractor.
✔ Correct Answer:
To plan, manage, monitor, and coordinate health and safety during pre-construction, ensuring foreseeable risks associated with temporary works interfaces are eliminated or controlled.