What is the main duty of the Principal Designer under CDM 2015 in relation to temporary works during the pre-construction phase?
Correct Answer:
To plan, manage, monitor, and coordinate health and safety during pre-construction, ensuring foreseeable risks associated with temporary works interfaces are eliminated or controlled.