AACE CST Practice Questions - AACE Certified Scheduling Technician Exam
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 4
Free Float is BEST defined as:
Time an activity can be delayed without delaying the project finish
Time an activity can be delayed without delaying the early start of any immediate successor
Time saved by crashing
Time between successive milestones
✔ Correct Answer:
Time an activity can be delayed without delaying the early start of any immediate successor
Count Down:
Related questions :