AACE CST Practice Questions - AACE Certified Scheduling Technician Exam

Access More Questions
Total Float for an activity is calculated as:
Correct Answer:
Late Finish - Early Finish (equivalently Late Start - Early Start)

Access more questions from this quiz

Continue to AACE CST Practice Questions - AACE Certified Scheduling Technician Exam for more practice questions and the full quiz experience.