A master painting contractor executes a facade coating project under a fixed lump-sum contract (Pauschalvertrag nach OR Art. 373). During the works, extreme unseasonal torrential rainfall exceeding 100-year historical records causes severe structural groundwater flooding and substrate saturation, preventing coating application for six weeks and causing substantial extra heating and dehumidification costs. Can the contractor claim price adjustments under OR Art. 373 Abs. 2?
Correct Answer:
Yes, if extraordinary, unforeseeable circumstances (ausserordentliche Umstände) arise that could not have been anticipated and render performance excessively onerous, a judge or arbitrator may adjust the lump sum or terminate the contract

Access more questions from this quiz

Continue to Malermeister in HFP Practice Questions - Malermeisterin Malermeister mit eidgenössischem Diplom (HFP) Maître peintre Exam for more practice questions and the full quiz experience.

Access More Questions