Question 1
A painting enterprise in the Canton of Zurich employs 12 journeymen painters under the Swiss Collective Employment Agreement for the Painting and Plastering Trade (GAV Maler- und Gipsergewerbe). During the busy summer season, several employees work 45 hours per week. How does the GAV annual working time model (Jahresarbeitszeitmodell) regulate weekly maximum working hours and the compensation of overtime (Überstunden)?
Correct Answer:
The GAV establishes an annual working time baseline (typically 2,080 hours/year or an average of 40.0–40.5 hours/week) with a seasonal bandwidth allowing up to 45 hours/week in peak periods, where hours within the bandwidth are credited to an annual time account (Arbeitszeitkonto) without immediate surcharge
Question 2
A painting contractor completes interior painting works for a commercial office building under a contract incorporating SIA-Norm 118. Fourteen months after the formal joint acceptance inspection (Gemeinsame Abnahmeprüfung), the client discovers hairline shrinkage cracks along several drywall corner joints and immediately notifies the contractor. How does SIA-Norm 118 regulate the defect notification period (Rügefrist) compared to statutory Swiss Code of Obligations (OR Art. 367)?
Correct Answer:
Under SIA-Norm 118 Art. 172/173, a 2-year guarantee period applies during which the client may report any defect at any time, in contrast to OR Art. 367 which requires immediate notice upon discovery
Question 3
A master painting contractor executes a facade coating project under a fixed lump-sum contract (Pauschalvertrag nach OR Art. 373). During the works, extreme unseasonal torrential rainfall exceeding 100-year historical records causes severe structural groundwater flooding and substrate saturation, preventing coating application for six weeks and causing substantial extra heating and dehumidification costs. Can the contractor claim price adjustments under OR Art. 373 Abs. 2?
Correct Answer:
Yes, if extraordinary, unforeseeable circumstances (ausserordentliche Umstände) arise that could not have been anticipated and render performance excessively onerous, a judge or arbitrator may adjust the lump sum or terminate the contract
Question 4
A painting enterprise completes extensive refurbishment works on a private villa in Bern on 30 April. The general contractor becomes insolvent and fails to pay the final outstanding invoice of CHF 45,000. To secure the claim via a mechanics' lien (Bauhandwerkerpfandrecht nach ZGB Art. 837 Abs. 1 Ziff. 3), by what strict statutory deadline must the provisional entry (provisorische Eintragung) be registered in the Land Register (Grundbuch)?
Correct Answer:
Within 4 months at the latest following the completion of the painting works (Vollendung der Arbeiten nach ZGB Art. 839 Abs. 2)
Question 5
Under the GAV Maler- und Gipsergewerbe, the Stiftung FAR (Frühzeitiger Altersrücktritt) provides an early retirement scheme for eligible operational workers in the painting trade. How is this foundation funded, and what is its primary benefit structure?
Correct Answer:
It is funded jointly by mandatory employer and employee payroll contributions (paritätische Beiträge), allowing eligible craft workers to retire up to 3 years prior to the statutory AHV retirement age with bridging pension benefits (Überbrückungsrente)
Question 1
Exam overview

About this Exam

Prepare with the Malermeister in HFP Practice Questions - Malermeisterin Malermeister mit eidgenössischem Diplom (HFP) Maître peintre Exam practice quiz. This question bank includes 100 questions covering painting, contractor, swiss, coating, and master. Use it to review important concepts, identify knowledge gaps, and build confidence for the related exam, course, or assessment.

More details

Additional Information

Malermeister in HFP Practice Questions - Malermeisterin Malermeister mit eidgenössischem Diplom (HFP) Maître peintre Exam

This practice set contains 100 questions from the matching question bank and focuses on painting, contractor, swiss, coating, and master. Work through each question carefully, review the provided solutions, and revisit topics that need more study before your next attempt.

This is an independent study resource intended for practice and review; it is not an official examination or an endorsement by any organization named in the title.

Quiz information

Frequently Asked Questions

The complete question count is available after full access is unlocked.
No fixed duration is currently configured for this quiz.
Question explanations are included where they are available in the quiz content, helping you review the reasoning after answering.
Yes. You can retake the practice test again as you continue studying during your available access period.
After your access is confirmed, you can continue into the complete practice exam from this quiz flow.
Unless explicitly stated otherwise, this page provides independent practice material for study and exam preparation and is not the official examination itself.
Keep studying

Related Questions