Question 1: A team is beginning an uncertain product initiative and expects
requirements to change as users see working increments. Which approach best reects an agile mindset?
Choices:
1) Create a detailed requirements baseline and reject changes after approval 2) Deliver small increments, gather feedback, and adjust priorities as learning occurs 3) Delay customer feedback until all planned features are complete 4) Assign all decisions to a project manager to preserve consistency Correct Answer: Deliver small increments, gather feedback, and adjust priorities as learning occurs Page 1
Explanation: Agile favors iterative delivery, frequent feedback, and adaptation. When uncertainty is high, small increments reduce the cost of learning and make changing priorities easier.Question 2: Which statement best reects the Agile Manifesto value concerning people and tools?
Choices:
1) Individuals and interactions are valued more than processes and tools 2) Processes and tools should replace informal team communication 3) Tools are more important than collaboration when work is distributed 4) Individuals and interactions matter only after a process is fully documented Correct Answer: Individuals and interactions are valued more than processes and tools Explanation: The Agile Manifesto values individuals and interactions over processes and tools.Processes and tools still have value, but they should support rather than dominate collaboration.
Question 3: A sponsor asks why an agile team does not attempt to freeze every
requirement at project start. What is the best response?
Choices:
1) Agile assumes requirements are unimportant 2) Agile eliminates planning until development is nished 3) Agile recognizes that feedback and changing conditions can improve what should be built 4) Agile requires customers to accept any scope change proposed by developers Correct Answer: Agile recognizes that feedback and changing conditions can improve what should be built Page 2
Explanation: Agile planning is continuous. Teams establish direction but expect learning, customer feedback, and market changes to rene requirements and priorities over time.
Question 4: Which outcome is the clearest example of incremental delivery?
Choices:
1) The team completes analysis for the entire product before any development begins 2) The team builds all components separately and integrates them only at the end 3) The team creates a complete technical design document before coding 4) The team releases a usable checkout improvement now and adds more checkout capabilities later Correct Answer: The team releases a usable checkout improvement now and adds more checkout capabilities later Explanation: Incremental delivery adds usable value in pieces. A working checkout improvement can provide value immediately while later increments extend the capability.Question 5: A team spends weeks producing extensive specications but has not demonstrated any functioning product. Which Agile Manifesto value is most directly at risk?
Choices:
1) Customer collaboration over contract negotiation 2) Working software over comprehensive documentation 3) Responding to change over following a plan 4) Individuals and interactions over processes and tools
Correct Answer: Working software over comprehensive documentation
Page 3