AACE CCP Practice Test Exam Prep 2026 Complete 119 Questions

EXAMS AND CERTIFICATIONS
Loading...

Loading secure study guide viewer...

Page 0 of 0

Document Text

AACE CCP PRACTICE TEST

EXAM PREP 2026

COMPLETE 119 QUESTIONS

Question 1: A project team needs an early screening estimate when scope de�nition is limited to major capacity and location. Which estimating approach is generally most appropriate?

Choices:

1) Detailed quantity takeo� 2) Parametric or analogous estimating 3) De�nitive vendor quotations 4) Bottom-up work-package estimating

Correct Answer: Parametric or analogous estimating

Explanation: With limited scope de�nition, parametric or analogous methods are appropriate for screening-level decisions because they use historical relationships rather than detailed quantities.Page 1

Question 2: Which item is most important to include in a basis of estimate so

another cost professional can understand how the estimate was developed?

Choices:

1) Only the �nal total cost 2) Assumptions, exclusions, pricing basis, and estimate methodology 3) Only the contingency percentage 4) The project organization chart Correct Answer: Assumptions, exclusions, pricing basis, and estimate methodology Explanation: A defensible basis of estimate documents the methodology, assumptions, exclusions, pricing basis, scope basis, and other information needed to understand and reproduce the estimate.Question 3: A scope change adds 1,200 m of piping. The validated installed unit rate is $185 per meter. What is the direct estimated cost of the added piping before indirects and contingency?

Choices:

1) $185,000

2) $210,000

3) $222,000

4) $240,000

Correct Answer: $222,000

Explanation: Direct cost = 1,200 x $185 = $222,000.

Page 2

Question 4: A historical plant cost $10.0 million at a capacity of 100 units per hour.Using a capacity factor exponent of 0.60, what is the estimated cost for 150 units per hour before other adjustments?

Choices:

1) $11.00 million 2) $12.75 million 3) $15.00 million 4) $16.50 million

Correct Answer: $12.75 million

Explanation: Use C2 = C1 x (Q2/Q1)^x. $10.0M x (1.5)^0.60 is about $12.75M.

Question 5: An estimate contains $5,000,000 of current-year cost that will be spent two years from now. If escalation is 3% per year compounded annually, what escalated amount should be budgeted?

Choices:

1) $5,150,000

2) $5,300,000

3) $5,304,500

4) $5,450,000

Correct Answer: $5,304,500

Explanation: Escalated cost = $5,000,000 x 1.03^2 = $5,304,500.

Page 3

Download Study Guide

Buy This Guide

$39.00 One-time purchase
Buy Now
  • Full access to this guide
  • Download anytime
  • No expiration

Study Guide Information

Category: EXAMS AND CERTIFICATIONS
Description:

AACE CCP PRACTICE TEST EXAM PREP 2026 COMPLETE 119 QUESTIONS Question 1: A project team needs an early screening estimate when scope de�nition is limited to major capacity and location. Wh...

Get this guide $39.00