Question 1
Which project delivery method describes a 'Standard of Care Relationship' with the A/E?
Correct Answer:
Standard of Care Relationship
Explanation:
The key idea here is how the Architect/Engineer is engaged and what duties they owe to the owner under a given delivery approach. A Standard of Care Relationship means the A/E provides professional design services under a contract that requires them to perform with the skill, care, and diligence that a reasonably prudent professional would exercise. The owner relies on that professional standard, and the A/E’s liability is tied to meeting it. This fits traditional methods where design and construction are separated: the A/E works under a professional services agreement, delivering designs that meet professional standards, rather than operating under a highly integrated or collaborative team structure. In more collaborative delivery approaches, the relationship shifts toward shared risk and joint decision-making, which is different from the strict standard-of-care liability model.
Question 2
For project-specific technical submittals, which procurement process and phase limits apply?
Correct Answer:
Two-phase
Explanation:
When a project has unique technical requirements that must be demonstrated by bidders, a two-phase procurement is used. In Phase I, the owner prequalifies teams to ensure they have the qualifications, experience, and capabilities to pursue the project. In Phase II, the shortlisted teams submit project-specific technical submittals that detail how they would meet the distinct technical performance requirements, often with price proposals evaluated afterward or in a separate step. This structure lets the owner assess technical capability and approach before considering cost, reducing risk of selecting a team that cannot meet the technical needs. Choosing a single, open, or purely price-focused process would not provide the same opportunity to verify how bidders intend to achieve the project’s technical goals, and a more complex three-phase approach is generally reserved for especially large or highly iterative programs.
Question 3
Which delivery method has a wide spectrum of contracting approaches?
Correct Answer:
Design-Build
Explanation:
Design-Build stands out because it combines design and construction under one contract, giving the owner flexibility to tailor how the project is priced and how risk is shared. With this delivery method, you can choose from a range of contract forms—lump-sum, cost-plus with a target or GMP, incentive-based arrangements, or other pricing structures—while still having a single point of responsibility for both design and construction. That flexibility lets the project adapt to budget, schedule, and risk preferences without changing delivery method. In contrast, design-bid-build follows a traditional sequence with separate contracts for design and construction and a more fixed pricing path after competitive bidding. Construction Manager at Risk focuses on a specific role for the CM with a GMP, which is just one way to structure preconstruction and cost risk. Integrated Project Delivery emphasizes collaboration among multiple parties under a distinct contractual framework, but it’s a different delivery approach rather than a broad set of contracting forms under one umbrella. So the ability to accommodate many contracting approaches within a single delivery method is a hallmark of design-build.
Question 4
Which description best captures the overall nature of Best Practices as presented?
Correct Answer:
High-Level Principles Organized into Three Topic Areas: Procurement, Contracting, and Execution
Explanation:
Best Practices describe high-level principles that guide how design-build projects are organized and delivered. They aren’t a rigid set of procedures; instead, they lay out overarching ideas you apply across the project lifecycle. The most fitting description groups these principles into three broad topic areas—Procurement, Contracting, and Execution—covering how you select the team and strategy, how you structure agreements and allocate risk, and how you manage design and construction toward integrated, value-driven outcomes. This framing reflects that Best Practices provide guiding principles across major phases rather than a single universal standard, and they aren’t merely optional or without impact—following them helps improve collaboration, risk management, and overall project outcomes.
Question 5
Which of the following is a type of requirement?
Correct Answer:
Functional
Explanation:
In DBIA practice, requirements are described in terms of what the project must do. Functional requirements specify the functions or services the building must provide for its users, focusing on the intended use and operations rather than prescribing exact solutions. This makes them a primary type of owner requirement because they set the what, not the how. The other terms describe different ideas: external considerations are factors outside the project’s design, performance requirements set measurable outcomes the project must meet, and prescriptive requirements specify particular materials or construction methods. Among these options, the SAMPLEone that directly names a category of requirement used to capture user and operational needs is the functional type.
Question 1
Exam overview

About this Exam

Prepare with the Design-Build Institute of America (DBIA) Exam 1 Practice practice quiz. This question bank includes 10 questions covering project, delivery, method, describes, and design-build. Use it to review important concepts, identify knowledge gaps, and build confidence for the related exam, course, or assessment.

More details

Additional Information

Design-Build Institute of America (DBIA) Exam 1 Practice

This practice set contains 10 questions from the matching question bank and focuses on project, delivery, method, describes, and design-build. Work through each question carefully, review the provided solutions, and revisit topics that need more study before your next attempt.

This is an independent study resource intended for practice and review; it is not an official examination or an endorsement by any organization named in the title.

Quiz information

Frequently Asked Questions

The complete question count is available after full access is unlocked.
No fixed duration is currently configured for this quiz.
Question explanations are included where they are available in the quiz content, helping you review the reasoning after answering.
Yes. You can retake the practice test again as you continue studying during your available access period.
After your access is confirmed, you can continue into the complete practice exam from this quiz flow.
Unless explicitly stated otherwise, this page provides independent practice material for study and exam preparation and is not the official examination itself.
Keep studying

Related Questions