PMI Risk Management Professional (PMI-RMP)

Access More Questions
You inform your project team during a status meeting that your risk register is only as good as the steps you take to manage the risk. If you don't also implement the responses, simply finding and documenting them won't assist. The overall risk exposure can only be handled pro-actively if ______ expends the necessary amount of effort in putting the responses into practice. You are talking about:
Correct Answer:
Risk owners

Access more questions from this quiz

Continue to PMI Risk Management Professional (PMI-RMP) for more practice questions and the full quiz experience.

Access More Questions