Civil Service Judgement Test
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
You are managing a small project. Midway through, a change in departmental priorities means your project's deadline has been moved forward by two weeks, and your resources have been slightly reduced. What is the most effective initial action to take?
Inform senior management that the new deadline is impossible to meet with the reduced resources.
Continue working as before and hope that the team can absorb the extra pressure.
Request that the project be cancelled as the new constraints make success unlikely.
Re-evaluate the project plan to identify non-essential tasks that can be de-scoped and reprioritise the remaining work with your team.
Reveal Answer
Correct Answer:
Re-evaluate the project plan to identify non-essential tasks that can be de-scoped and reprioritise the remaining work with your team.