Why does the EPA Construction General Permit provide reduced inspection and stabilization timing for arid and semi-arid areas such as much of New Mexico?
Correct Answer:
Because a seasonally dry month is defined as one whose long-term average precipitation is 0.5 inch or less, when runoff risk is lower