Who determines the survey party and its components for a Geodetic Control Survey?
Correct Answer:
The Chief of Party or the Project Contractor
Explanation:
The person who actually sets up the field crew for a geodetic control survey is the on-site lead—the Chief of Party—often acting for the Project Contractor when the work is contracted. This role is responsible for organizing the survey party, deciding its size and the specific positions (such as field crew roles and qualifications) based on the project’s scope, required accuracy, safety, and practical logistics. If a contractor is involved, they may propose the staffing plan, but it remains under the Chief of Party’s supervision to ensure it meets contract terms and technical standards. Higher-level offices like NAMRIA, regional executives, or departmental administrators oversee policy, funding, or program direction, not the day-to-day configuration of the survey team.

Access more questions from this quiz

Continue to DMC Department Administrative Order (DAO) No. 2007-29 Practice Test for more practice questions and the full quiz experience.

Access More Questions