CMPM Practice Exam
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Which term describes the function of approving budgets, changes, and scope?
Oversight
Control
Risk Management
Decision-Making
Reveal Answer
Correct Answer:
Control
Explanation:
This question tests naming the function that approves budgets, changes, and scope—the control activities that keep a project aligned with its plan. The best term is control, because this function encompasses monitoring performance, comparing it to the plan, and authorizing any deviations. Approving the budget, reviewing proposed changes, and validating scope adjustments all fall under integrated change control and baseline management, which are core parts of the control process. They ensure that only justified, approved modifications are implemented, preserving the integrity of the project’s baselines. Oversight involves supervising and monitoring activities but doesn’t specifically capture the formal process of approving changes and budgets. Risk management focuses on identifying and mitigating potential problems rather than the authorization of changes. Decision-making describes choosing among options but doesn’t inherently include the formal approval of budgeting, scope, and changes as part of governance.