Arizona Appraiser Licensing Practice Exam

Access More Questions
Which of the following is the correct sequence for a construction change process?
Correct Answer:
Request for Information, Construction Change Directive, Change Order
Explanation:
Typically, an RFI is submitted, which may lead to a CCD if terms aren't agreed upon, finally culminating in a formal Change Order.