When installing a two-valve bottom blowdown line on a high-pressure steam boiler (operating above 100 psig), in what sequence should the valves be arranged from the boiler shell outward?
Correct Answer:
A quick-opening valve closest to the boiler shell, followed by a slow-opening valve