When a water main and sanitary sewer must cross under ADEM 335-7-7 (after January 1, 2013, unless otherwise approved), how is separation completed with casing?
Correct Answer:
Place a continuous casing around one of the mains so there is a minimum five-foot separation between each end of the cased main and the uncased main