NM CID GS-8 Practice Questions - New Mexico CID GS-8 Earthmoving, Excavation And Ditching Examination Exam

Access More Questions
When a support (shoring) system is removed from an excavation, OSHA 1926.652(e) requires that removal:
Correct Answer:
Begin at, and progress from, the bottom, with members released slowly and backfilling progressing together with removal

Access more questions from this quiz

Continue to NM CID GS-8 Practice Questions - New Mexico CID GS-8 Earthmoving, Excavation and Ditching Examination Exam for more practice questions and the full quiz experience.