Cost Controls Practice Test
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
What is the purpose of statusing in project management?
To document team assignments.
To compare actual progress and cost to the baseline.
To estimate the project duration.
To approve changes to scope.
Reveal Answer
Correct Answer:
To compare actual progress and cost to the baseline.
Explanation:
Tracking project health by comparing what happened with what was planned is what statusing is all about. After you set a baseline for scope, schedule, and cost, statusing captures current progress and expenditure and compares them to that baseline. This reveals variances in time and money, helps you forecast whether the project will finish on time and within budget, and signals when corrective actions are needed. It also supports clear communication with stakeholders about how the project is actually performing. Documenting team assignments fits more with resource management and staffing. Estimating project duration is a planning activity. Approving changes to scope belongs to change control.
Access more questions from this quiz