A project has a planned duration of 200 calendar days. After 50 days, 20% of the work is complete. If progress continues at the same rate, what is the projected total duration?
Correct Answer:
250 days
Explanation:
At 20% completion in 50 days, the implied total duration is 50 / 0.20 = 250 days.