What is the difference between a 'Change Order' and a 'Construction Change Directive' (CCD)?
Correct Answer:
A CCD is used when there is no agreement on cost or time yet
Explanation:
A CCD is used to direct work when the owner and contractor have not yet agreed on a price or time change.