A contract amendment changes key deliverables and due dates. How should the contract manager treat the change?
Correct Answer:
As a potentially material change requiring review of risk and monitoring needs
Explanation:
Changes to significant deliverables, pricing, dates, or other substantive terms may be material and can require approvals, updated risk assessment, and revised monitoring.