I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
A project specification requires a 6-hour minimum recoat interval, while the coating manufacturer's current PDS states 8 hours under the recorded conditions. What should the inspector do before the next coat is applied?
Use the shorter interval because the specification always overrides all technical data
Use an average of 7 hours
Seek clarification from the authorized project representative and document the discrepancy
Allow the contractor to choose either value
Reveal Answer
Correct Answer:
Seek clarification from the authorized project representative and document the discrepancy
Explanation:
Conflicting project requirements should be resolved by the authorized party before work proceeds. The inspector should identify and document the conflict rather than unilaterally changing requirements.
Access more questions from this quiz
Continue to Telc Practice Test & Exam Prep for more practice questions and the full quiz experience.