A project specification requires a 6-hour minimum recoat interval, while the coating manufacturer's current PDS states 8 hours under the recorded conditions. What should the inspector do before the next coat is applied?
Correct Answer:
Seek clarification from the authorized project representative and document the discrepancy
Explanation:
Conflicting project requirements should be resolved by the authorized party before work proceeds. The inspector should identify and document the conflict rather than unilaterally changing requirements.