SC Pre-Engineered Metal Buildings Practice Questions - South Carolina Pre-Engineered Metal Buildings Contractor Examination Exam

Access More Questions
Unless a high-early-strength mix or the project specification says otherwise, newly placed concrete should be kept moist and above about 50°F for at least:
Correct Answer:
3 days for high-early-strength concrete or 7 days for standard portland-cement concrete

Access more questions from this quiz

Continue to SC Pre-Engineered Metal Buildings Practice Questions - South Carolina Pre-Engineered Metal Buildings Contractor Examination Exam for more practice questions and the full quiz experience.