Under the Massachusetts Prompt Payment Act (M.G.L. c. 149, Section 29E), which applies to private construction contracts of $3 million or more, what is the maximum period to approve or reject a subcontractor's periodic payment application after submission?
Correct Answer:
15 days (plus 7 additional days per contract tier below the owner)