Under the EPA 2022 Construction General Permit, which inspection choice is available for a typical construction site that does not discharge to a sensitive water?
Correct Answer:
Inspect at least once every 7 calendar days, or at least once every 14 calendar days and within 24 hours of a 0.25-inch storm