Under section 3.7.5 why would the contractor immediately suspend work or a portion of work?
Correct Answer:
The contractor exposes human remains, burial markers, archaeological sites, or wetlands not indicated in the contract documents
Explanation:
Immediate suspension is required when the site reveals an unanticipated condition that could have legal or safety implications. Under section 3.7.5, if the contractor exposes human remains, burial markers, archaeological sites, or wetlands that are not indicated in the contract documents, work in the area must be stopped right away and the architect and owner must be notified to determine the proper course of action. This keeps protected resources from being disturbed and ensures compliance with legal and regulatory requirements, as well as follows the contract’s process for handling unexpected site conditions. Other scenarios, like poor weather, a change being requested by the architect, or delays caused by the owner, are handled through different contractual provisions or procedures and do not automatically mandate an immediate suspension under this clause.

Access more questions from this quiz

Continue to AIA Contract Document A201 Practice Test for more practice questions and the full quiz experience.

Access More Questions