Under Regulation 11(1) of the Electricity Regulations 1994, wiring or rewiring of an installation, or an extension to an existing installation, must be carried out by whom, with prior written approval obtained from a licensee or supply authority?
Correct Answer:
An Electrical Contractor or a Private Wiring Unit (PWU)