NM CID GF-2 Practice Questions - New Mexico CID GF-2 Bridges Contractor Examination Exam

Access More Questions
Under NMDOT Section 104, if the Department considers a Value Engineering Change Proposal (VECP) and then refuses it, the Contractor is entitled to:
Correct Answer:
No Contract Time extension for the Department’s consideration or refusal of the VECP

Access more questions from this quiz

Continue to NM CID GF-2 Practice Questions - New Mexico CID GF-2 Bridges Contractor Examination Exam for more practice questions and the full quiz experience.