MA General Contractor Practice Questions - Massachusetts General Contractor Exam

Access More Questions
Under M.G.L. Chapter 254, Section 4, what must a sub-subcontractor (a party without a direct contract with the general contractor) do to protect the full amount of their mechanic's lien rights?
Correct Answer:
Send a written notice of identification to the general contractor by certified mail, return receipt requested, within 30 days of commencing performance

Access more questions from this quiz

Continue to MA General Contractor Practice Questions - Massachusetts General Contractor Exam for more practice questions and the full quiz experience.

Access More Questions