Under Arizona Revised Statutes (A.R.S. § 40-360.22) and Arizona 811 (Blue Stake) regulations, how far in advance of beginning excavation for fence post footings must a contractor notify utility owners?
Correct Answer:
At least 2 working days prior to beginning excavation, excluding weekends and state holidays