AL Water Projects Practice Questions - Alabama Water Projects Contractor Examination Exam

Access More Questions
Under Alabama’s One-Call law (Code of Alabama § 37-15-4), when must an excavator notify Alabama 811 before starting a water-main excavation?
Correct Answer:
At least two but not more than 10 working days prior to the start, not including the day of notification

Access more questions from this quiz

Continue to AL Water Projects Practice Questions - Alabama Water Projects Contractor Examination Exam for more practice questions and the full quiz experience.

Access More Questions