AL Sitework Practice Questions - Alabama Sitework Contractor Examination Exam

Access More Questions
Under Alabama 811 practices, what is the minimum advance notice generally required before planned excavation (not counting the day of notification)?
Correct Answer:
At least 2 working days (and typically within a 2–10 working day window) before the proposed start

Access more questions from this quiz

Continue to AL Sitework Practice Questions - Alabama Sitework Contractor Examination Exam for more practice questions and the full quiz experience.