Befähigungsprüfung Bauträger Practice Questions - Austria Befähigungsprüfung Bauträger (Property Developer Licensing Examination) Exam

Access More Questions
Under § 1 Abs. 1 of the Austrian Developer Contract Act (Bauträgervertragsgesetz - BTVG), what is the advance payment threshold per square metre that triggers the mandatory protective scope of the BTVG?
Correct Answer:
Advance payments exceeding €150 per m² of usable floor space (Nutzfläche) made prior to completion

Access more questions from this quiz

Continue to Befähigungsprüfung Bauträger Practice Questions - Austria Befähigungsprüfung Bauträger (Property Developer Licensing Examination) Exam for more practice questions and the full quiz experience.