Two stormwater alternatives have equal service life. Alternative 1 has a present worth cost of $1.25 million, while Alternative 2 has a present worth cost of $1.38 million. Ignoring non-cost factors, which option is economically preferred?
Correct Answer:
Alternative 1 because it has the lower present worth cost