A project has BAC = $1,000,000, EV = $400,000, AC = $500,000, PV = $450,000. Both cost and schedule trends are expected to continue. Which EAC formula applies and what is the result (rounded)?
Correct Answer:
EAC = AC + ((BAC − EV) / (CPI × SPI)) ≈ $1,344,000

Access more questions from this quiz