Per NRS 455.110, before beginning a non-emergency excavation in an area that is known or reasonably should be known to contain subsurface installations, the excavator must notify the association for operators (Nevada 811 / USA North) how far in advance?
Correct Answer:
At least 2 working days but not more than 28 calendar days before the excavation is scheduled to start