Per NMDOT 2019 Section 618.2.4, the Contractor shall develop and maintain alternate traffic-signal timing plans for long-term temporary traffic control lasting longer than how many calendar days, and who must stamp that work?
Correct Answer:
Five calendar days; a licensed Professional Engineer in New Mexico