SC Public Utilities Electrical Practice Questions - South Carolina Public Utilities - Electrical Contractor Examination Exam

Access More Questions
OSHA 1926.1408 states that power lines are presumed energized unless the utility owner/operator confirms that the line has been and continues to be:
Correct Answer:
Deenergized and visibly grounded at the worksite

Access more questions from this quiz