On an automatically fired gas or oil boiler, the main fuel train is required to include which shutoff arrangement?
Correct Answer:
Automatic safety shutoff valve(s) that close on any interlock trip (typically two valves in series on larger CSD-1/NFPA 85 trains) plus a manual tightness-test provision