On a site where a sewer trench will be cut through a small ridge and the spoil will fill a sag along the same alignment, what is a cut-and-fill balance?
Correct Answer:
Planning the work so the volume of suitable excavated material, after swell and shrinkage, is enough to build the required fills with little waste or borrow