Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
ATI Nursing
CNA & Nurse Aide
NREMT & EMS
ACLS
BLS
CPR
Quizzes
Study Guides
Flashcards
Packages
0
Log In
Register
Categories
All Categories
DMV
ServSafe
OSHA
NCLEX
HESI
TEAS
Quizzes
Study Guides
Flashcards
Packages
Contact
Cart
0
Log In
Register
B2 Commercial Building Inspector Practice Test
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 5
Excavation for a spread footing exposes loose fill where the approved geotechnical report requires bearing on competent native soil. What should the inspector require before concrete placement?
Verify that the bearing surface is corrected or approved by the design/geotechnical professional before placement
Place concrete immediately to prevent rain exposure
Increase concrete slump to fill voids
Add a vapor retarder under the footing
✔ Correct Answer:
Verify that the bearing surface is corrected or approved by the design/geotechnical professional before placement