Many flooring adhesive manufacturers and flooring industry standards cite 75% relative humidity as the maximum allowable in-situ RH level for installing resilient flooring over concrete. If a slab tests at 78% RH, the correct course of action is to:
Correct Answer:
Delay installation and allow additional drying time or apply a vapor mitigation system before installing flooring