What can you do in Timeline and Gantt view regarding dependencies?
Correct Answer:
Visually see tasks with dependencies and create new ones by drawing connections.
Explanation:
In Timeline and Gantt views, dependencies are shown as visual links between task bars, indicating the sequence that must be followed. You can create a new dependency by drawing a connection from one task to another, which locks the second task to wait for the first to finish. This setup helps you plan work flow, see which tasks are blocked, and watch how changes to one task affect its dependents—the schedule automatically adjusts for linked tasks. The other options don’t reflect how dependencies work in this view: changing colors, editing descriptions, or importing dependencies from Excel aren’t how you manage task dependencies in Timeline.