Based on a simulation: 50% chance of three-week schedule delay; using the risk table, what is the correct Level and Schedule Impact?
Correct Answer:
L = 3; Schedule Impact 4
Explanation:
This item tests how a risk table translates probability of occurrence and the magnitude of a schedule effect into numeric risk ratings. A 50% chance sits in the middle for likelihood, and in the risk table this mid-range likelihood is assigned a Level 3. A three-week delay is a significant schedule hit, and on the schedule-impact scale this magnitude is typically rated high (often a 4). When these two inputs are entered into the risk table, they map to a risk level of 3 and a Schedule Impact of 4, which is why the correct result is Level 3 with Schedule Impact 4. This combination communicates a moderate overall risk with a substantial effect on the schedule, signaling that mitigation should address both reducing likelihood and limiting impact where possible.

Access more questions from this quiz

Continue to PMT 4910 Advanced Certification Practice Exam for more practice questions and the full quiz experience.

Access More Questions