An estimate contains $5,000,000 of current-year cost that will be spent two years from now. If escalation is 3% per year compounded annually, what escalated amount should be budgeted?
Correct Answer:
$5,304,500
Explanation:
Escalated cost = $5,000,000 x 1.03^2 = $5,304,500.