IMC 1108.3.1 requires which inert-gas procedure before and during brazing?
Correct Answer:
Pre-purge for a minimum of five volume changes at not less than 100 ft/min, then maintain 1.0 to 3.0 psi of inert gas during brazing; filler metal shall conform to AWS A5.8