How many days prior to the scheduled activity must the DTL secure a permit from HSFRB/CHD?
Correct Answer:
10 working days
Explanation:
Securing a permit well before the event is about matching the regulatory review timeline. The DTL must obtain the permit from HSFRB/CHD at least ten working days prior to the scheduled activity. This lead time gives the regulatory office a window to review the submission, request any needed clarifications or corrections, and issue the permit in time for the activity to proceed legally. Working days exclude weekends and holidays, so planning around that ensures the permit arrives in hand before the event. Ten working days strikes a practical balance between allowing enough processing time and avoiding last‑minute delays.