For a natural-turf soccer field in an arid New Mexico park, which finished-grade strategy is most appropriate when the plans do not show a subsurface drain grid?
Correct Answer:
A consistent sheet-drain slope, commonly on the order of 1 to 1.5 percent, or a gentle crown, so surface water leaves the playing surface